[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389941,172,1,"单选题","大型复杂项目的项目管理有别于单项目管理，对于大型复杂项目来说，首先应该制订的计划是 （请作答此空） 。而在该计划中一般不会包括 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度计划",false,{"key":16,"text":17,"correct":14},"B","成本计划",{"key":19,"text":20,"correct":14},"C","范围计划",{"key":22,"text":23,"correct":24},"D","过程计划",true,"一般项目会主要关注项目的活动计划，但是对于大型复杂的项目，必须首先考虑项目的过程计划，也就是先确定什么方法和过程来完成项目。所谓过程就是通过系统的方法和步骤来实现一个预定的目标。对于大型项目，则必须建立以过程为基础的管理体系，而不是以活动为基础。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]