[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389894,172,1,"单选题","一般，项目计划主要关注项目的 （请作答此空） ，但是对大型复杂项目来说，必须优先考虑制订项目的 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","活动计划",true,{"key":16,"text":17,"correct":18},"B","过程计划",false,{"key":20,"text":21,"correct":18},"C","资源计划",{"key":23,"text":24,"correct":18},"D","组织计划","对于一般项目而言，主要关注的是项目的活动计划。但是对于大型及复杂项目要先确定果用什么方法和过程来完成项目，即在活动计划前要先确定过程计划。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]