[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389869,172,1,"单选题","Before a project schedule can be created,the schedule maker should have a （ ） ,an effort estimate for each task,and a resource list with availability for each resource.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","work breakdown structure",true,{"key":16,"text":17,"correct":18},"B","baseline",false,{"key":20,"text":21,"correct":18},"C","software requirements specification",{"key":23,"text":24,"correct":18},"D","plan","翻译：在项目进度计划制定前，制定者应该有一份工作分解结构，一份针对每个任务的工作量估算，以及可用资源列表。A．工作分解结构 B．基线 C．软件需求说明书 D．计划",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]