[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389867,172,1,"单选题","Project schedule management is made up of six management processes including: activity definition, activity sequencing, （ ） , and schedule control by order．",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","activity duration estimating, schedule developing, activity resource estimating",false,{"key":16,"text":17,"correct":18},"B","activity resource estimating, activity duration estimating, schedule development",true,{"key":20,"text":21,"correct":14},"C","schedule developing, activity resource estimating, activity duration estimating",{"key":23,"text":24,"correct":14},"D","activity resource estimating, schedule developing, activity duration estimating","项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来，合理分配工作量，利用进度安排的有效分析方法来严格监视项目的进展情况，以使得项目的进度不致被拖延。项目时间管理过程包括：活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序，因此选择“活动的资源估算”、“活动历时估算”、制订进度计划，所以选B。（71） A．活动历时估算 制订进度计划 活动的资源估算 B．活动的资源估算 活动历史估算 制订进度计划 C．制订进度计划 活动的资源估算 活动历时估算 D．活动的资源估算 制订进度计划 活动历时估算",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]