[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389864,172,1,"单选题","Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with, project stakeholders. The （ ） is useful responsible for stakeholder management.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","PMO",false,{"key":16,"text":17,"correct":14},"B","CIO",{"key":19,"text":20,"correct":14},"C","CCB",{"key":22,"text":23,"correct":24},"D","PM",true,"项目干系人管理是指为满足干系人的需要而与之沟通，并解决所发生的问题。通常，项目经理（PM）负责项目干系人管理。A．项目管理办公室 B．首席信息官 C．变更控制委员会 D．项目经理",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]