[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389863,172,1,"单选题","（ ） describes，in detail，the project’s deliverables and the work required to create those deliverables.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","Product scope description",false,{"key":16,"text":17,"correct":14},"B","Project objectives",{"key":19,"text":20,"correct":14},"C","Stakeholder Analysis",{"key":22,"text":23,"correct":24},"D","The project scope statement",true,"项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。（72） A．产品范围说明书 B．项目目标 C．干系人分析 D．项目范围说明说",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]