[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389859,172,1,"单选题","Establishing a project management timetable involves listing milestones,activities,and（ ）with intended start and finish dates,of which the scheduling of employees may be an element.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","relationships",false,{"key":16,"text":17,"correct":14},"B","resources",{"key":19,"text":20,"correct":14},"C","stakeholders",{"key":22,"text":23,"correct":24},"D","deliverables",true,"翻译：建立一个项目管理时间表包括列出里程碑，活动，以及开始和结束日期的目标交付物，其中员工是计划中的一个要考虑的要素。A．关系 B．资源 C．干系人 D．交付物",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]