[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389856,172,1,"单选题","The （ ） process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Quantitative Risk Analysis",true,{"key":16,"text":17,"correct":18},"B","Qualitative Risk Analysis",false,{"key":20,"text":21,"correct":18},"C","Risk Monitoring an",{"key":23,"text":24,"correct":18},"D","Control","项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中，风险识别过程是确定哪些风险可能会对项目产生影响，并将这些风险的特征形成文档。 A．风险识别 B．定量风险分析 C．定性风险分析 D．风险检测与控制",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]