[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389839,172,1,"单选题","In the process of communication requirement analysis，the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law，a project with 10 stakeholders has （ ） potential communication channels.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","45",true,{"key":20,"text":21,"correct":14},"C","50",{"key":23,"text":24,"correct":14},"D","100","在沟通过程的需求分析中，项目经理应该考虑项目沟通的复杂性，将潜在的沟通渠道或路径的数量作为一个指标来计算。根据麦特卡夫定律，一个项目有10个项目干系人的时候，将有（73）条潜在的沟通渠道。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]