[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389838,172,1,"单选题","Changes may be requested by any stakeholder involved with the project，but changes can be authorized only by （ ） ．",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","executive IT manager",false,{"key":16,"text":17,"correct":14},"B","project manger",{"key":19,"text":20,"correct":21},"C","change control board",true,{"key":23,"text":24,"correct":14},"D","project sponsor","项目变更可以由执行经理（executive IT manager）、项目管理者（project manager）、项目发起人（project sponsor）等任意项目干系人发起，但只能由变更控制委员会（change control board）授权通过。（73） A．执行经理 B．项目经理 C．变更控制委员会 D．项目发起人",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]