[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389836":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389836,172,1,"单选题","( ) must be between on-line deployment and final acceptance.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Detailed design",false,{"key":16,"text":17,"correct":18},"B","Test run",true,{"key":20,"text":21,"correct":14},"C","Internal testing",{"key":23,"text":24,"correct":14},"D","Contract signing","翻译： 一定是处于上线部署和最终验收之间。 A.详细设计 B.试运行 C.内部测试 D. 合同的签订",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]