[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389833,172,1,"单选题","Precedence Diagramming Method（PDM） is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called （ ）.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Finish-to-Start",true,{"key":16,"text":17,"correct":18},"B","Finish-to-Finish",false,{"key":20,"text":21,"correct":18},"C","Start-to-Start",{"key":23,"text":24,"correct":18},"D","Start-to-Finish","前导图法是用于活动排序的技术。前导图法包括四种活动依赖关系。先行活动结束后续活动才能开展的关系是结束—开始关系。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]