[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389829,172,1,"单选题","The schedule management plan is a component of the project management plan The schedule management plan maybe formal or informal,highly detailed or broadly framed,based up on the（ ）of the project,and includes appropriate control thresholds.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","goals",false,{"key":16,"text":17,"correct":14},"B","values",{"key":19,"text":20,"correct":21},"C","needs",true,{"key":23,"text":24,"correct":14},"D","Level","翻译：进度管理计划是项目管理计划的一个组成部分，根据项目的（需求），项目计划管理计划可以是正式的或非正式的，高度详细的或概括的，并包括适当的控制阈值。A．目标 B．价值C．需求 D．水平",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]