[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389826,172,1,"单选题","（ ）estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Parametric",false,{"key":16,"text":17,"correct":18},"B","Analogous",true,{"key":20,"text":21,"correct":14},"C","Three-point",{"key":23,"text":24,"correct":14},"D","Expert judgment","类比估计是一项使用类似的活动或项目的历史数据，来估计活动的时间或成本的技术。 （73） A．参数 B．类比 C．三点 D．专家判断",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]