[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389823,172,1,"单选题","（ ） is the process of documenting. Analyzing，tracing，prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","Integrated management",false,{"key":16,"text":17,"correct":14},"B","Configuration management",{"key":19,"text":20,"correct":14},"C","Scope management",{"key":22,"text":23,"correct":24},"D","Requirements management",true,"需求管理是一个记录的过程。对需求进行分析、描绘、划分优先顺序，达成需求并控制其变化、并传达给利益相关者，它在项目中是一个持续的过程。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]