[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389822,172,1,"单选题","The most crucial time for project risk assessment is （ ） .",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","when a problem surfaces",false,{"key":16,"text":17,"correct":18},"B","during the planning phase",true,{"key":20,"text":21,"correct":14},"C","during the close-out phase",{"key":23,"text":24,"correct":14},"D","after the project schedule has been published","进行项目风险评估最关键的时候是规划阶段。A．问题出现时 B．规划阶段 C．结束阶段 D．项目进度公布后",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]