[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389810,172,1,"单选题","Your project is behind schedule due to conflict between team members. Having resolved the conflict，to get the project back on schedule，you should consider （ ） .",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","crashing the schedule",false,{"key":16,"text":17,"correct":18},"B","performing resource leveling",true,{"key":20,"text":21,"correct":14},"C","conducting reverse resource allocation scheduling",{"key":23,"text":24,"correct":14},"D","utilizing the critical chair resources","由于团队成员之间的冲突，造成了项目进度落后于计划，为了解决冲突以使得项目如期完成你应该考虑。A．重新安排时间表 B．执行资源调配C．进行反向资源分配调度 D．利用关键的主要资源",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]