[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389798":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389798,172,1,"单选题","Estimating activity durations uses information on activity scope of （ ） , required resource types, estimated resource quantities, and resource calendars.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","milestone",false,{"key":16,"text":17,"correct":14},"B","baseline",{"key":19,"text":20,"correct":14},"C","quality",{"key":22,"text":23,"correct":24},"D","work",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]