[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389796":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},389796,172,1,"单选题","Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and（ ）. A.fast tracking",[11,15,19],{"key":12,"text":13,"correct":14},"A","what-if scenario analysis",true,{"key":16,"text":17,"correct":18},"B","resource leveling",false,{"key":20,"text":21,"correct":18},"C","critical chain metho","进度压缩技术包括赶工和快速跟进。（74） A．快速跟进 B．假设情景分析 C．资源平衡 D．关键链法",{"id":6,"name":24,"category":25,"favorite":26},"(高级)信息系统项目管理师","职业资格",0]