[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389786,172,1,"单选题","The cost performance index（CPI） is the ratio of earned value to （ ） and can be used to estimate the projected cost of completing the project.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A. cost variance",false,{"key":16,"text":17,"correct":14},"B","B.planne cost",{"key":19,"text":20,"correct":14},"C","Planne value",{"key":22,"text":23,"correct":24},"D","actual cost",true,"翻译： 成本绩效指数是挣值和（ ）的比率，用来估算完成整个工程的预计费用。 A. 成本差值 B. 计划成本 C. 计划值 D. 实际花费",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]