[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389784":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389784,172,1,"单选题","After acceptance and formal transfer of information systems to customers,it has entered the stage of（ ）. A.preparation",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","operation an",false,{"key":16,"text":17,"correct":18},"B","maintenance",true,{"key":20,"text":21,"correct":14},"C","development",{"key":23,"text":24,"correct":14},"D","Extinction","翻译：信息系统在正式移交给客户后，就入了运行和维护阶段A．准备 B．运行与维护C．开发 D．消亡",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]