[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389783,172,1,"单选题","The （） technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex. A.Cost Aggregation",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Reserve Analysis",false,{"key":16,"text":17,"correct":14},"B","Parametri",{"key":19,"text":20,"correct":21},"C","Estimating",true,{"key":23,"text":24,"correct":14},"D","Funding Limit Reconciliation","参数估算涉及在一个数学模型中利用项目特性来预测整体项目成本，模拟可以是简单的也可以是复杂的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]