[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389782,172,1,"单选题","（） are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Controls",false,{"key":16,"text":17,"correct":14},"B","Baselines",{"key":19,"text":20,"correct":21},"C","Project stakeholders",true,{"key":23,"text":24,"correct":14},"D","Project managers","项目干系人是积极参与到项目中，或其利益可能会受到项目执行或完成结果影响的个人或组织，他们可能会对项目及其结果施加影响。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]