[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389781,172,1,"单选题","The scope management plan is how the team will prepare the（ ）a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","project charter",false,{"key":16,"text":17,"correct":14},"B","project scope goal",{"key":19,"text":20,"correct":14},"C","project budget",{"key":22,"text":23,"correct":24},"D","project scope statement",true,"翻译：范围管理计划是团队如何准备项目范围说明文件，包括描述创建WBS，核实项目的可交付成果的完成，并为项目范围变更控制的要求。A．项目章程 B．项目范围目标C．项目预算 D．范围说明书",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]