[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389780,172,1,"单选题","setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this? （ ） ．",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","risk avoidance",false,{"key":16,"text":17,"correct":14},"B","risk acceptance",{"key":19,"text":20,"correct":21},"C","risk mitigation",true,{"key":23,"text":24,"correct":14},"D","contingency plan","翻译：为子系统设置冗余组件处理原系统带来的风险，是一种什么样的风险应对策略？A．风险规避 B．风险接受C．风险减轻 D．应急计划冗余减少了风险发生概率，属于风险减轻。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]