[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389779,172,1,"单选题","The creation of a work breakdown structure（WBS）is the process of （ ） the major project deliverables.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","subdividing",true,{"key":16,"text":17,"correct":18},"B","assessing",false,{"key":20,"text":21,"correct":18},"C","planning",{"key":23,"text":24,"correct":18},"D","integrating","创建工作分解结构是分解项目可交付物的过程。A．分解 B．估算 C．计划 D．整合",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]