[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389766,172,1,"单选题","Requirements management is the process of （73） ，analyzing，tracing，prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders．",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","communicating",false,{"key":16,"text":17,"correct":14},"B","collecting",{"key":19,"text":20,"correct":14},"C","filing",{"key":22,"text":23,"correct":24},"D","documenting",true,"需求管理是针对需求进行（过程记录），分析，跟踪，优先考虑，控制变更并与相关干系人沟通的过程。 A．沟通 B．收集 C．归档 D．编制、记录",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]