[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389752,172,1,"单选题","某软件的工作量是20000行，由4人组成的开发小组开发，每个程序员的生产效率是5000行\u002F人月，每对程序员的沟通成本是250行\u002F人月，则该软件需要开发 （ ） 月。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","1.04",{"key":19,"text":20,"correct":14},"C","1.05",{"key":22,"text":23,"correct":24},"D","1.08",true,"这里考查沟通路径计算，4个程序员沟通路径= n×(n-1)\u002F2=4×（4-1）\u002F2=6条。设定软件开发需要Y月，则沟通量+工作量=开发总量6×250×Y+20000=4×5000×Y得到Y=1.08",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]