[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389744,172,1,"单选题","下图是一个选择出行路线的“决策树图”，统计路线1和路线2堵车和不堵车的用时和其发生的概率（P），计算出路线1和路线2的加权平均用时，根据计算结果选择出行路线。以下结论中，正确的是（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","路线1的加权平均用时为4 0.5分钟，路线2的加权平均用时为4 8分钟，因此选择路线1",true,{"key":16,"text":17,"correct":18},"B","路线1的加权平均用时为6 2.5分钟，路线2的加权平均用时为4 0分钟，因此选择路线2",false,{"key":20,"text":21,"correct":18},"C","路线1的加权平均用时为4 0.5分钟，路线2的加权平均用时为4 4分钟，因此选择路线1",{"key":23,"text":24,"correct":18},"D","由于路线2堵车和不堵车时间都比路线1短；因此选择路线2","路线1: 35*0.90+90+0.1=40.5；路线2: 20*0.30+60+0.7=48；",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]