[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389725,172,1,"单选题","某项目的工期为40周，每周可以使用12个小时，若用于完成该项目所有活动的资源只有192个工时，则此时项目资源使用率为 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.2",false,{"key":16,"text":17,"correct":18},"B","0.4",true,{"key":20,"text":21,"correct":14},"C","0.8",{"key":23,"text":24,"correct":14},"D","1","项目的资源使用率=项目资源\u002F项目完成需要工时。由于项目工期为40周，每周为12个小时，项目完成需要480个工时，但是项目资源只有192个，因此项目的资源使用率为192\u002F480=0.4。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]