[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389695,172,1,"单选题","某大型布线项目由甲、乙两个子项目组成。甲项目场地准备3天，乙项目场地准备需2天；甲项目施工需5天，乙项目施工需4天。两个项目的场地准备都需要一台专用设备。在只有一台可用的专用设备的情况下，此大型项目至少需要 （ ） 天才能完成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","10","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]