[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389691,172,1,"单选题","某车间需要用一台车床和一台铣床加工 A、 B、 C、D四个零件。每个零件都需要先用车床加工，再用铣床加工。车床和铣床加工每个零件所需的工时（包括加工前的准备时间以及加工后的处理时间）如下表。 若以 A、 B、 C、D零件顺序安排加工，则共需29小时。适当调整零件加工顺序，可产生不同实施方案，在各种实施方案中，完成四个零件加工至少共需（ ） 小时。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","25",false,{"key":16,"text":17,"correct":18},"B","26",true,{"key":20,"text":21,"correct":14},"C","27",{"key":23,"text":24,"correct":14},"D","28","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]