[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389685,172,1,"单选题","一个活动有4道工序，一个工人只能负责1道工序。每名工人工作完成各工序所需小时数如下表所示，工序间的依赖关系如下表所示。完成该活动最少需要 （ ） 个小时。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","16",true,{"key":23,"text":24,"correct":14},"D","18","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]