[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389674,172,1,"单选题","某软件工程项目各开发阶段工作量的比例如下表所示。 假设当前已处于编码阶段，3000行程序已完成了1200行，则可估算出该工程项目开发进度已完成的比例是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","43%",false,{"key":16,"text":17,"correct":14},"B","49%",{"key":19,"text":20,"correct":21},"C","57%",true,{"key":23,"text":24,"correct":14},"D","63%","目前已处于编码阶段，即需求分析、概要设计、详细设计均已完成。编码完成了1200\u002F3000=40%，完成比例为：0.23+0.11+0.15+0.2 ? 40%=0.57",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]