[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389655,172,1,"单选题","依据GB\u002FT8566-2007《信息技术软件生存周期过程》中有关配置管理的规定，（ ）是配置控制的任务。①建立基线的文档②批准或否决变更请求③审核跟踪变更④确定和保证软件项针对其需求的功能完备性、物理完整性分析和评价变更⑤分析和评估变更⑥编制配置管理计划⑦实现、验证和发布已修改的软件项",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②③⑤⑦",true,{"key":16,"text":17,"correct":18},"B","①③⑤⑥",false,{"key":20,"text":21,"correct":18},"C","①③⑤⑦",{"key":23,"text":24,"correct":18},"D","②④⑥⑦","配置控制：1、标识并记录变更申请；2、分析与评价变更；3、批准或不批准申请；4实现、验证和发行已经变更的软件项；5、审核跟踪变更；6、控制并审核受控软件项。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]