[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389636,172,1,"单选题","某软件系统投入运行10天，计划运行时间为每早8点至晚6点。第二天上午发生一次失效，故障恢复用了1小时。第4天上午发生一次失效，故障恢复用了4小时。第9天上午发生一次失效，故障恢复用了1小时。根据《软件工程产品质量GB\u002F16260—2006》，该软件系统的有效性（或可用性，availability）为 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","98%",false,{"key":16,"text":17,"correct":14},"B","95%",{"key":19,"text":20,"correct":14},"C","80%",{"key":22,"text":23,"correct":24},"D","94%",true,"有效性：在要求的外部资源得到保证的前提下，产品你在规定的条件下和规定的时刻或 时间区间内处于可执行规定功能状态的能力。它是产品可靠性、维修性和维修保障性的综合反映。该软件系统运行时间为每早8点至晚6点，每天10个小时，在这10个小时中该软件系统的有效性为（10′10-1-4-1）\u002F﹙10′10﹚=94%。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]