[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389599,172,1,"单选题","根据《软件工程术语GB\u002FT11457—2006》，验证过程试图确保活动的输出产品已经被正确制造，而确认过程则试图确保建造了正确的产品。因此，项目组为保证系统的设计满足需求规格说明书要求而实施的过程称为 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","架构验证",false,{"key":16,"text":17,"correct":14},"B","需求确认",{"key":19,"text":20,"correct":14},"C","架构确认",{"key":22,"text":23,"correct":24},"D","需求验证",true,"根据验证和确认的定义，为保证系统的设计满足需求规格说明书要求而实施的过程是对需求的验证而不是确认。因为系统的设计方案再优秀，也不一定能够保证建造了正确的产品。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]