[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389530":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389530,172,1,"单选题","某企业以公开招标方式选择承建方，下列做法中， （ ） 是违反《中华人民共和国招标投标法》规定的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设方未委托招标代理机构，自行编制招标文件和组织评标",false,{"key":16,"text":17,"correct":14},"B","建设方在开标前组织潜在投标人踏勘项目现场",{"key":19,"text":20,"correct":14},"C","建设方在提交投标文件截止日前第15日修改招标文件，书面通知所有招标文件收受人",{"key":22,"text":23,"correct":24},"D","建设方在招标文件中确定发出招标文件后的第15日为投标人提交投标文件截止之日",true,"中华人民共和国招标投标法规定：依法必须进行招标的项目，自招标文件开始发出日起至投标人提交截止之日止，最短不少于20日。选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]