[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389512,172,1,"单选题","某企业在招标时，首先通过某种资格审查选择部分供应商，并以邮件问询的方式确定它们是否有兴趣参与竞标，然后将采购文件包发给所有有兴趣的供应商，并对供应商反馈的投标文件进行评估，最终将中标消息通知给中标的供应商。以下关于本次招标过程的判断，正确的是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目招标之前该企业不应当事先进行资格筛选",false,{"key":16,"text":17,"correct":14},"B","意见征询不应通过邮件的方式进行",{"key":19,"text":20,"correct":14},"C","中标结果不应仅凭评估分数确定",{"key":22,"text":23,"correct":24},"D","在选定供应商后，招标结果不应只反馈给中标供应商",true,"《中华人民共和国招投标法》第四十五条：中标人确定后，招标人应当向中标人发出中标通知书，并同时将中标结果通知所有未中标的投标人。故选D。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]