[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389463,172,1,"单选题","项目初步设计方案和投资概算报告的编制内容与项目可行性研究报告批复内容有重大变更或变更投资超出已批复总投资额度（ ）的",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%",true,{"key":16,"text":17,"correct":18},"B","15%",false,{"key":20,"text":21,"correct":18},"C","20%",{"key":23,"text":24,"correct":18},"D","30%","项目初步设计方案和投资概算报告的编制内容与项目可行性研究报告批复内容有重大变更或变更投资超出已批复总投资额度10%的",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]