[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389450,172,1,"单选题","在投标文件的报价单中，如果出现总价金额和分项单价与工程量乘积之和的金额不一致时，应当 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","以总价金额为准，由评标委员会直接修正即可",false,{"key":16,"text":17,"correct":14},"B","以总价金额为准，由评标委员会修正后请该标书的投标授权人予以签字确认",{"key":19,"text":20,"correct":14},"C","以分项单价与工程量乘积之和为准，由评标委员会直接修正即可",{"key":22,"text":23,"correct":24},"D","以分项单价与工程量乘积之和为准，由评标委员会修正后请该标书的投标授权人予以签字确认",true,"在投标文件的报价单中，如果出现总价金额和分项单价与工程量乘积之和的金额不一致时，应当以分项单价与工程量乘积之和为准，由评标委员会修正后请该标书的投标授权人予以签字确认。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]