[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389422":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389422,172,1,"单选题","某公司在制订招标评分标准时，下列做法较合适的是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对业绩评定的标准是：好、不好",false,{"key":16,"text":17,"correct":14},"B","服务能力评定标准是：根据其通过ISO20000认证情况酌情打分",{"key":19,"text":20,"correct":21},"C","价格分采用低价优先法计算",true,{"key":23,"text":24,"correct":14},"D","按照ISO9000认证情况，将质量标准分为7个档次","根据《关于加强政府采购货物和服务项目价格评审管理的通知》的规定：政府采购货物和服务项目采用综合评分法的，综合评分法中的价格分统一采用低价优先法计算，即满足招标文件要求且投标价格最低的投标报价为评标基准价，其价格分为满分。其他投标人的价格分统一按照下列公式计算：投标报价得分=（评标基准价／投标报价）?价格权值?100，采购人或其委托的采购代理机构对同类采购项目采用综合评分法的，原则上不得改变评审因素和评分标准。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]