[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389393,172,1,"单选题","在项目组合管理中，确定项目优先级的主要决定因素是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的进度",false,{"key":16,"text":17,"correct":14},"B","项目组合的收益",{"key":19,"text":20,"correct":14},"C","项目总成本",{"key":22,"text":23,"correct":24},"D","组织战略",true,"项目发起人的最终目的是通过实现技术项目来实现组织战略。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]