[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389389,172,1,"单选题","对于大型及复杂项目而言，在制订活动计划之前，必须要确定用什么方法和过程来完成项目。 （ ） 就是满足这一要求的项目管理方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过程计划",true,{"key":16,"text":17,"correct":18},"B","基准计划",false,{"key":20,"text":21,"correct":18},"C","生命周期计划",{"key":23,"text":24,"correct":18},"D","统一的项目过程","对大型及复杂项目来说，制订活动计划之前，必须先考虑项目的过程计划，也就是必须先确定用什么方法和过程来完成项目，建立统一的项目过程会大大提高项目之间的协作效率，有力保证项目质量。也就是说：过程计划是项目管理方法，建立统一的项目过程 是其中一种措施，但不一定都要建立统一的项目过程。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]