[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389386,172,1,"单选题","在项目组合管理中，项目排序是对项目创造的 （ ） 和投入进行分析，以选择出对组织最有利项目的过程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","功能性交付物",false,{"key":16,"text":17,"correct":14},"B","交付物",{"key":19,"text":20,"correct":14},"C","期望货币值",{"key":22,"text":23,"correct":24},"D","期望价值",true,"项目选择和优先级排列过程是对项目创造的期望价值和投入进行分析，以选择出对组织最有利项目的过程。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]