[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389385,172,1,"单选题","有关大型及复杂项目管理的说法中， （ ） 是错误的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大型项目经理的日常职责更集中于管理职责",false,{"key":16,"text":17,"correct":18},"B","大型项目管理模式接近于直接管理模式",true,{"key":20,"text":21,"correct":14},"C","在大型项目中应明确大项目经理和子项目经理各自的职责",{"key":23,"text":24,"correct":14},"D","在大型项目中应建立统一的项目过程","大型项目管理多采用间接管理模式。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]