[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389383":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389383,172,1,"单选题","项目组合管理实施的主要过程不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评估项目组合管理战略计划",true,{"key":16,"text":17,"correct":18},"B","定义项目组合管理的愿景和计划",false,{"key":20,"text":21,"correct":18},"C","实施项目组合管理过程",{"key":23,"text":24,"correct":18},"D","改进项目组合管理过程","项目组合管理的实施过程主要包括：（1）评估项目组合管理过程的当前状态（2）定义项目组合管理的愿景和计划（3）实施项目组合管理过程（4）改进项目组合管理过程",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]