[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389378":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389378,172,1,"单选题","在对大型及复杂项目实施跟踪和控制的过程中，需要重点关注的环节是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对项目过程的持续改进",false,{"key":16,"text":17,"correct":14},"B","对项目总体计划的实时更新",{"key":19,"text":20,"correct":21},"C","加强绩效报告的有效性并处理好项目的变更",true,{"key":23,"text":24,"correct":14},"D","确定项目实现其质量目标的方法","在对大型及复杂项目实施跟踪和控制的过程中，最关键的环节是获取项目的实施绩效，和项目的基准计划进行比较。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]