[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389373":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389373,172,1,"单选题","关于典型的大型、复杂信息系统项目，下列做法中， （ ） 是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目团队构成复杂，不仅包括项目内部人员体系，也包括合作方人员体系",false,{"key":16,"text":17,"correct":14},"B","项目规模较大，目标构成复杂，往往分解成目标相互关联的小项目",{"key":19,"text":20,"correct":21},"C","项目沟通成本大幅度上升，项目经理应该直接管理各子项目内的沟通",true,{"key":23,"text":24,"correct":14},"D","项目管理方法与小型项目相比发生了根本的改变","对于大型复杂信息系统项目，项目经理应间接管理各子项目内的沟通，这样可以节约成本。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]