[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389364,172,1,"单选题","在滚动式计划中，____ 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关注长期目标，允许短期目标作为持续活动的一部分进行滚动",false,{"key":16,"text":17,"correct":18},"B","近期要完成的工作在工作分解结构最下层详细规划",true,{"key":20,"text":21,"correct":14},"C","远期要完成的工作在工作分解结构最下层详细规划",{"key":23,"text":24,"correct":14},"D","为了保证项目里程碑，在战略计划阶段做好一系列详细的活动计划","滚动式计划是项目渐进明细的表现形式，近期要完成的工作在工作分解结构的最下层详细计划，而计划远期完成的工作在工作分解结构的较高层计划。最近一两个报告期要进行的工作应在本期接近完成前更为详细地计划。所以，项目计划在项目生命期内可以处于不同的详细水平。在信息不够确定的早期战略计划期间，活动的详细程度可能只到里程碑的层次。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]